District 6 of the Ohio Department of Transportation has planned the following work in the Morrow County area on the specified dates and times. All work is weather dependent; it may be postponed or cancelled without prior notice.
The following work is planned in the Morrow County area on the specified dates and times. All work is weather dependent; it may be postponed or cancelled without prior notice.
Interstate 71
I-71 will be reduced to one lane in each direction at the Richland County Line from 8 p.m. to 6 a.m. for resurfacing. The project is set to be completed July 21.
Craven Road
Starting at 7 a.m.,Craven Road will close in both directions between Carpenter Road and Woodbury-Bellville Road for two months for bridge replacement as part of the Ohio Bridge Partnership Program. The detour is Craven Road to the Morrow/Richland County Line to Woodbury-Bellville Road to Craven Road or reverse. The project is set to be completed Sept. 9.
State Route 97
State Route 97 will be reduced to one lane of traffic between Crawford County Line and Richland County Line from 6:30 a.m. to 11:30 p.m. for pavement work. Traffic will be maintained by flaggers. The project is set to be completed Sept. 30.
State Route 288
State Route 288 will be reduced to one lane of traffic between State Route 309 and State Route 97 from 6:30 a.m. to 11:30 p.m. for pavement work and resurfacing. Traffic will be maintained by flaggers. The project is set to be completed Sept. 30.
State Route 521
Beginning at 7 a.m., State Route 521 will be closed over I-71 for bridge replacement. The detour is State Route 521 to State Route 61 to US 36 to State Route 521 or reverse. The project is slated to be completed in November.
Ongoing work
County Road 30
County Road 30 (Gilead-Iberia-Galion Road) will close between West Point Bellville Road and St. James Road for a bridge replacement. The detour is County Road 30 (Gilead-Iberia-Galion Road) to County Road 51 (St. James Road) to State Route 61 to County Road 29 (W. Point Bellville Road) to County Road 30 (Gilead-Iberia-Galion Road) or reverse. The project is set to be completed in July
County Road 23
County Road 23 is closed over I-71 for a bridge replacement. The detour is County Road 172 (Jackson Road) to County Road 25 (Waldo-Fulton-Chesterville Road) to County Road 20 (Williamsport-Bloomingrove Road) or reverse. The project is set to be completed in July
U.S. Route 42
S 42 is reduced to one lane between the Delaware County Line and Mount Gilead – Sunbury Road from 7 a.m. to 5 p.m. for pavement resurfacing. Traffic will be maintained daily with flaggers. The project is set to be completed Aug. 31.
County Road 15
County Road 15 (W. Liberty Mt. Vernon Road) will close over I-71 for a bridge replacement. The detour is County Road 15 to State Route 61 to Watson Road to Berkshire South Drury Road to County Road 15 or reverse. The project is set to be completed Sept. 15.